Legislation Details

File #: 24-0801   
Type: County Manager Status: Passed
File created: 5/8/2024 In control: Board of County Commissioners
On agenda: 5/21/2024 Final action: 5/21/2024
Title: Approve Amendment No. 1 with AECOM, Inc. for Agreement 2021-016, construction engineering and inspection services (CEI) for the West Pipkin Road widening project. ($635,525.62 one-time expense)
Attachments: 1. Amend 1 Contract 2021-016 5-8-24

SUBJECT

title

Approve Amendment No. 1 with AECOM, Inc. for Agreement 2021-016, construction engineering and inspection services (CEI) for the West Pipkin Road widening project. ($635,525.62 one-time expense)

body

 

DESCRIPTION

The County entered into an agreement with AECOM, In. on March 2, 2021, to perform contract administration, and inspection services for the West Pipkin Road from Medulla Road to SR 37 construction project for a total not-to-exceed amount of $3,076,701.05.

West Pipkin Road is a two-lane collector road in south Lakeland that connects County Line Road to SR 37 (South Florida Avenue).  To address level of service (LOS) issues due to growth and development in the area, Polk County is planning to widen West Pipkin Road from two lanes to four lanes to add capacity and improve the LOS.  The limits of the widening project are from Medulla Road to SR 37.  The section from Medulla Road to Old Hwy 37 is scheduled to be four-laned.  The section from Dorman Road to SR 37 is scheduled to be three-laned.

The County needs to add additional services to the scope of work, to include additional CEI staffing for inspection/tracking due to contractor utilizing more crews than anticipated to ensure construction time frames are met; along with additional subconsultant services for borings and vibration monitoring in the amount of $635,525.62.

The total Agreement amount is increased to $3,712,226.67.

The term of this agreement is through completion of construction.

 

RECOMMENDATION

Request Board approve amendment No. 1 with AECOM, Inc. in regard to agreement 2021-016, construction engineering and inspection services for West Pipkin Road widening in the amount of $635,525.62.

 

FISCAL IMPACT

Funds are available in the Roads and Drainage Transportation Millage Fund.

 

CONTACT INFORMATION

Michael Guerrero

Sr. Procurement Contract Analyst

Procurement

(863) 534-6716

michaelguerrero@polk-county.net