Title: Approve the Mitigation Credit Purchase and Deposit Agreement with the Tippen Bay Wetland Mitigation Bank to purchase 3.57 Freshwater State Herbaceous (UMAM) credits for the functional wetland habitat impacts on the CR 557 Widening Project. ($499,800.00 one-time expense)
Attachments: 1. 7-9-24 Final TBWMB Purchase Agreement X CR 557 Widening, 2. 2. REQ for Legal_Fillable rev. 102821
SUBJECT
title
Approve the Mitigation Credit Purchase and Deposit Agreement with the Tippen Bay Wetland Mitigation Bank to purchase 3.57 Freshwater State Herbaceous (UMAM) credits for the functional wetland habitat impacts on the CR 557 Widening Project. ($499,800.00 one-time expense)
body

DESCRIPTION
On December 26, 2018, the Board Approved Professional Service Agreement #18-073 (Agreement) with Dewberry Engineers, Inc. to provide professional engineering services in connection with the CR 557 Widening Project including developing and evaluating alternative roadway design and alignment, recommending a preferred alignment, and preparing preliminary roadway plans for the widening in the amount of $1,100,893.47.
On September 1, 2020, the Board approved Amendment No. 1 to the Agreement with Dewberry Engineers, Inc. to provide final design services for the CR 557 Widening project including permitting, final design, bidding support, and community awareness services in the amount of $3,040,982.53, bringing the total cost of the Agreement to $4,141,876.00.
On December 6, 2022, the Board approved Amendment #2 to the Agreement with Dewberry Engineers, Inc. to develop and evaluate alternative roadway design and alignments, provide a recommendation, and prepare preliminary and final plans for improvements to the CR 557 @ US 17/92 intersection in Lake Alfred at a not-to-exceed fee of $693,396.38, bringing the total cost of the Agreement to $4,835,272.38.
On August 22, 2023, the Board approved Amendment #3 to the Agreement with Dewberry Engineers, Inc., to design a surcharge program required to stabilize the soils for roadway construction, to prepare lighting plans for the entire length of the project, and to prepare a stand-alone set of plans for construction of the CR 557 @ Old Lake Alfred Road Roundabout to facilitate advanced construction of the intersection. The cost of the additional design services for Amendment #3 was a not-to-exceed fee of $429,107.94, bringing the...