Title: Approve 1) construction contract with Bul-Hed Corporation for the Lake Annie water quality improvement project, and 2) CIP amendment and budget transfer in the amount of $720,000.00 with in the American Rescue Plan and Stormwater MSTU Funds. ($3,300,300.14 one-time expense)
Attachments: 1. CIP Amendment Request, 2. 24-464 Part E - Contract_vendor signed, 3. SKM_C750i24111416051

SUBJECT

title

Approve 1) construction contract with Bul-Hed Corporation for the Lake Annie water quality improvement project, and 2) CIP amendment and budget transfer in the amount of $720,000.00 with in the American Rescue Plan and Stormwater MSTU Funds. ($3,300,300.14 one-time expense)

body

 

DESCRIPTION

The Parks and Natural Resources Division requested Procurement to solicit bids from qualified contractors who were interested in making improvements to altered wetlands (previously a peat mine) and uplands along the Peace Creek Canal. The stormwater infrastructure site is located near the intersection of Lincoln Avenue and US Highway 27 in Dundee, FL. This project will consist of removing invasive vegetation and replanting with native vegetation, improving the perimeter berms, and increasing the inflow and outflow of water which will result in the restoration of the wetlands and improve stormwater treatment.  This project is a multiyear project.

 

Bid 24-464, Lake Annie Water Quality Improvement Project was issued, and one contractor submitted a bid.

Company

Location

Total

Bul-Hed Corporation

Mulberry, FL

$3,143,143.14

 

A recommendation of award was issued to Bul-Hed Corporation and no protests were received. In accordance with Resolution No. 13-066, 5% was added for allowance work in the amount of $157,157.00 for a total contract amount of $3,300,300.14. Allowance time for the project is 54 days.

 

This bid came in higher than projected in the Capital Improvement Plan (CIP), therefore a CIP amendment and transfer is necessary to fully fund the project.

 

The total CIP budget for this project is $2,880,426.00.  Other project related costs to include design and other soft costs are estimated at $300,125.86, leaving a balance of $2,580,300.14 available for construction. Therefore, a CIP Amendment is needed in the amount of $720,000.00 to fund the construction project.

 

Staff is recommending that the $720,000 needed to fully fund the project be re-allocated and transferred from the Small-Scale Surface Water Enhancement/Treatment Project ($546,464.00 ARP Funds) and the Lake Lulu Project ($173,536.00 Stormwater MSTU Funds).

 

The Lake Annie Water Quality Improvement Project is currently funded in part through the American Rescue Plan (ARP) through the United States Department of Treasury. After the recommended CIP amendment, the ARP will total $1,042,642.00 for this construction. The Florida Department of Environmental Protection (FDEP) Grant Agreement #LPA0436 named Peace Creek Water Preservation Project with Polk County will provide $1,000,000.00 and the remaining contract cost of $1,257,658.14 will come from the Stormwater MSTU.

 

RECOMMENDATION

Request Board approve 1) construction contract with Bul-Hed Corporation for $3,300,300.14 for Bid 24-464, Lake Annie Water Quality Improvement Project, and 2) CIP amendment and budget transfer in the amount of $720,000.00 with in the Stormwater MSTU and American Rescue Plan Funds.

 

FISCAL IMPACT

Funds in the amount of $720,000.00 are available for transfer in the American Rescue Plan and Stormwater MSTU Funds.  Total construction costs will be split between the American Rescue Plan ($1,042,642.00), Special Revenue Grants ($1,000,000.00), and the Stormwater MSTU Funds ($1,257,658.14).

CONTACT INFORMATION

Brad Howard

Sr. Procurement Analyst