Title: Approve agreement with Eisman & Russo, Inc. for construction engineering and inspection (CEI) services for Thompson Nursery Road Phase I - Segment 1. (not-to-exceed one-time expense $5,010,675.00)
Attachments: 1. RFP 25-245 Agreement Vendor Signed
Date Action ByActionResultAction DetailsAgenda DetailsVideo
No records to display.

SUBJECT

title

Approve agreement with Eisman & Russo, Inc. for construction engineering and inspection (CEI) services for Thompson Nursery Road Phase I - Segment 1. (not-to-exceed one-time expense $5,010,675.00)

body

 

DESCRIPTION

Thompson Nursery Road (TNR) is a proposed four-lane urban collector roadway located to the south of Winter Haven. The corridor limits of the Project are from the intersection of US 17 @ SR 540 to the intersection of TNR @ US 27 (approximately 10 miles).

Polk County has identified the construction of TNR as a priority given the population and employment growth projected for the region surrounding TNR. This expected growth is evident in the increased traffic demands on nearby roadways, and future development projects planned along the corridor.

On June 7, 2022, the County entered into an agreement with Kimley-Horn and Associates, Inc. for professional engineering services for the TNR project. This project will require a separate engineering firm to provide construction administration, inspection, and quality control services once the construction of the project commences. It is anticipated that construction will begin in March 2026.

Roads and Drainage requested Procurement to solicit proposals for the purpose of providing CEI services for the Thompson Nursery Road project.

Request for Proposal (RFP) 25-245, Construction Engineering & Inspection Services for TNR was issued, and five vendors submitted proposals. On April 15, 2025, the Board approved the committee’s recommendation to enter into contract negotiations with Eisman & Russo, Inc. The attached agreement is the result of those negotiations.

The Scope of Work includes the following Tasks:

A. General Contract Administration

B. On-Site Inspection and Oversight

C. Sampling and Testing

D. Construction Contract Management

E. Utility Coordination

F. Stormwater and Environmental Compliance

G. Public Involvement & Documentation

H. Quality Assurance and Plan

I. Contractor Final Payment Request

Eisman & Russo will provide the following positions to perform this Scope of Work with an estimated 38,354 Hours:

Senior Project Engineer

Project Administrator/Utility

Office Manager/Admin

EEO Compliance

Lead Senior Inspector

Senior Inspector

Senior Inspector - Utilities

Inspector

Inspector

Inspector (3G) (DBE)

Inspector (RCS) (DBE)

Inspector - Aide

Sr. Environmental Specialist

 

 It is anticipated that the project will conclude in February 2028, yet the term of the agreement will be until all services are complete for TNR Phase I - Segment 1. Finally, the County retains the right to retain the Consultant and negotiate additional CEI Services for the Construction of TNR PH I - Segment 2 & 4 and TNR PH II.

 

RECOMMENDATION

Request Board approve the agreement with Eisman & Russo, Inc. (Consultant) for construction engineering & inspection services for Thompson Nursery Road Phase I - Segment 1 in the amount of $5,010,675.00.

 

FISCAL IMPACT

Funds are budgeted in the Transportation Impact Fee Fund Zone A.

 

CONTACT INFORMATION

Ken Brush

Procurement Contracts Manager

Procurement

(863) 534-6727

kenbrush@polk-county.net