Legislation Details

File #: 26-2281   
Type: County Manager Status: Passed
File created: 11/4/2026 In control: Board of County Commissioners (Organizational)
On agenda: 11/17/2026 Final action: 11/17/2026
Title: Approve the Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) Addendum No. 4 to Agreement 2023-074 with Wharton-Smith, Inc. for the Northeast Regional Wastewater Facility (NERWWTF). ($75,930,310.00 one-time expense)
Attachments: 1. Con 2023-074 GMP #4_vendor signed, 2. Tab 1, 3. Tab 2, 4. Tab 3, 5. Tab 4, 6. Tab 5 Schedule

SUBJECT

title

Approve the Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) Addendum No. 4 to Agreement 2023-074 with Wharton-Smith, Inc. for the Northeast Regional Wastewater Facility (NERWWTF). ($75,930,310.00 one-time expense)

body

 

DESCRIPTION

On December 5, 2023, the Board entered into Agreement 2023-074, with Wharton-Smith, Inc., to provide pre-construction CMAR services for the NERWWTF expansion from 6 to 9 million gallons daily (MGD) project to be completed in 2 phases.

On September 17, 2024, the Board approved Amendment No. 1 to the agreement for additional pre-construction services in anticipation of the following 5 GMP’s to be approved by the Board:

•                     GMP #1: Phase A-Deep Bed Filters, Chlorine Contact Chambers, Dewatering, Chemical Feed Building

•                     GMP #2: Phase A-Electrical and Communication Improvements, Phase E Other Plant-wide Improvements (e.g. generator replacements, switching from medium voltage to now voltage)

•                     GMP #3: Phase B-Headworks, Return Pump Station, Electrical Building No. 3

•                     GMP #4: Phase C-Biological Nutrient Removal, Equalization Tank, Splitter Box Blower/MCC Building

•                     GMP #5: Phase D-Ground Storage Reservoir, High Service Pump Station, Augmentation Wells

On December 17, 2024, the Board approved GMP No. 1 in the amount of $41,644,133.00, to construct Phase A - Deep Bed Filters, Chlorine Contact Chambers, Dewatering, and Chemical Feed Building.

On February 28, 2025, the Board approved GMP No. 2 in the amount of $30,421,036.00, to construct Phase A- Electrical and Communication Improvements, Phase E Other Plant-wide improvements (e.g. generator replacements, switching from medium voltage to low voltage).

On November 4, 2025, the Board approved GMP No. 3 in the amount of $50,825,822.00, to construct Phase B - Construction of electrical building No. 3 and purchase the headworks, return pump station equipment.

Pre-construction services for Phase C-Biological Nutrient Removal, Equalization Tank, Splitter Box Blower/MCC Building, which includes design and bidding services, are now complete, and Wharton-Smith has provided the attached GMP No. 4 in the amount of $75,930,310.00 to construct these improvements.

The total contract time for GMP No. 4 is 1,271 calendar days. In accordance with Resolution 2026-047, allowance time for this project is 190 calendar days.

Due to rapid growth in the service area, the construction of this GMP will increase capacity incrementally while the design and GMPs are being completed for additional phases.

It is anticipated that GMP Addendum No. 5, to provide construction of ground storage reservoirs, high service pump station, and augmentation wells will be ready for Board approval in 2027.

 

RECOMMENDATION

Request Board approve Construction Manager at Risk (CMAR), Guaranteed Maximum Price (GMP) Addendum No. 4 to Agreement 2023-074 with Wharton-Smith, Inc. for the Northeast Regional Wastewater Facility (NERWWTF) in the amount of $75,930,310.00.

 

FISCAL IMPACT

Funding is available in the Utilities Five-Year Community Investment Program Budget.

 