SUBJECT
title
Approve construction contract with Strickland Construction, Inc. for new office and maintenance buildings at Saddle Creek Park project ($3,809,996.00 one-time expense)
body
DESCRIPTION
The Facilities Management Division requested Procurement solicit bids from qualified contractors to construct a +- 4,766 SF office building and +- 4,100 SF office/storage building at and associated parking and stormwater management system at Saddle Creek Park located at 3716 Morgan Combee Road, Lakeland.
As a result of a site assessment, performed in 2023, the existing Saddle Creek Park maintenance office facility was identified to have structural concerns, building envelope deficiencies, and water intrusion. The assessment concluded that significant remedial work would provide only a temporary solution and that new facilities were needed to support efficient operations and maintain the required level of service. Construction of a new office and maintenance buildings at a separate location within Saddle Creek Park will allow operations to continue during construction.
Bid 26-372, Saddle Creek New Office and Maintenance Buildings was issued, and sixteen contractors submitted a bid.
Company Location Total________
Strickland Construction, Inc. Lakeland, FL $3,463,633.00
Henkelman Construction, Inc. Lakeland, FL $3,481,207.00
Mar Con Construction, LLC Clermont, FL $3,497,800.00
d/b/a MARBEK Construction, Inc.
Stellar Development, Inc. Sarasota, FL $3,545,162.78
Everett Whitehead & Son, Inc. Winter Haven, FL $3,549,665.00
d/b/a Whitehead Construction
Mulligan Constructors, Inc. Orlando, FL $3,607,777.00
Quest Contracting, LLC West Palm Beach, FL $3,656,508.00
Storage Building Company, LLC Bradenton, FL $3,724,999.56
The Diaz/Fritz Group, Inc. Tampa, FL $3,733,136.00
Erickson & Lindstrom Construction Co. Largo, MI $4,006,800.00
NuJak Companies, Inc. Lakeland, FL $4,096,716.00
SEMCO Construction, Inc. Bartow, FL $4,120,000.00
LEMA Construction, Inc. St. Petersburg, FL $4,190,723.00
L Cobb Construction, Inc. Wauchula, FL $4,225,467.02
Imperial Construction & Electric, Inc. Springfield, NJ $4,444,000.00
FSV Construction Company Miami, FL $5,000,000.00
A recommendation of award was issued to Strickland Construction, Inc. and no protests were received. In accordance with Resolution No. 2026-052, $346,363.00 was added to the contract for allowance work for a total contract amount of $3,809,996.00.00. The contract time for this project is 300 calendar days for final completion. Allowance time for the project is 45 days.
RECOMMENDATION
Request Board approve construction contract with Strickland Construction, Inc. for the new office and maintenance buildings at Saddle Creek Park project in the amount of $3,809,996.00
FISCAL IMPACT
Funds are budgeted and available in the five-year Parks and Natural Resources CIP within the Leisure Services MSTU Fund.
CONTACT INFORMATION
Colin Burke
Procurement Analyst
863.534.6749
colinburke@polkfl.gov <mailto:colinburke@polkfl.gov>