Approve Construction Contract No. 2021-052, Change Order No. 4 with Vogel Brothers Building Co. for the Upgrade Lift Station No. 253 (Providence) Project. ($12,216.47 increase; $2,217 CIP amendment and transfer from reserves; revised contract sum to date of $892,638.61, and time extension of 155 days).
body
DESCRIPTION
Construction contract 2021-052 with Vogel Brothers Building Company for the Upgrade Lift Station No 253 project was approved by the Board on July 6, 2021. The summary of the contract total and subsequent change orders is as follows:
|
Item |
Board Approval |
Additional Time |
Amount |
New Contract Total |
|
Contract Approval |
July 6, 2021 |
NA |
$1,250,092.20 |
$1,250,092.20 |
|
Deductive CO #1 |
April 12, 2022 |
NA |
($108.003.58) |
$1,142,088.62 |
|
Deductive CO #2 plus time extension |
May 25, 2022 |
249 days |
($261,666.48) |
$880,422.14 |
|
CO #3 - time extension only |
April 13, 2023 |
162 days |
NA |
$880,422.14 |
|
CO #4 plus time extension |
Current |
155 days |
$12,216.47 |
$892,638.61 |
After conception of this project, Polk County Utilities adopted a policy that in addition to a standby generator, regional lift stations will include permanent by-pass pumps. This will aid in reduction of sanitary sewer overflows in the event of a power outage as well as accommodating maintenance and repairs to the lift station. The County requested a change order to add the permanent by-pass pumps. This change, as well as some additional temporary by-pass pumping required during construction, totaled $176,744.67. The summary of the change order is provided on Attachment A.
The contract amount of $1,250,092.20 included contingencies and allowance totaling $164,528.20 consisting of the following:
Electrical Contingency $ 35,000.00
Instrumentation and Control Contingency $ 35,000.00
Civil/Site Contingency $ 35,000.00
Allowance Work $ 59,528.20
This agenda item is requesting an additional $12,216.47 is to cover Change Order No. 4. In addition, a time extension of 155 days is requested to complete the additional work. The Board approval of Change Order Number 4 will supersede and satisfy the need for other customary contingency release and allowance authorization.
The new contract total will be $892,638.61. The project budget is short $2,217 and requires a CIP amendment.
RECOMMENDATION
Approve Construction Contract No. 2021-052, Change Order No. 4 with Vogel Brothers Building Co. for the Upgrade Lift Station No. 253 (Providence) Project and CIP amendment and transfer from reserves. ($12,216.47 increase; $2,217 CIP amendment and transfer from reserves; revised contract sum to date of $892,638.61, and time extension of 155 days).
FISCAL IMPACT
Upon the approval of a CIP amendment and transfer from reserves in the amount of $2,217, funding is available in the Utilities Capital Expansion Fund to complete this project.