Title: Approve Construction Contract No. 2021-052, Change Order No. 4 with Vogel Brothers Building Co. for the Upgrade Lift Station No. 253 (Providence) Project. ($12,216.47 increase; $2,217 CIP amendment and transfer from reserves; revised contract sum to date of $892,638.61, and time extension of 155 days).
Attachments: 1. Vogel Brothers Building Co., (Contract No. 2021-052) - Change Order No. 4 - Upgrade Lift Station 253 (Providence) Project - Agenda Request (Revised), 2. Vogel Brothers Building Co., (Contract No. 2021-052) - Change Order No. 4 - Upgrade Lift Station 253 (Providence) Project - Project Request (Signed), 3. Vogel Brothers Building Co., (Contract No. 2021-052) - Change Order No. 4 - Upgrade Lift Station 253 (Providence) - Change Order No. 4 (Signed By Director & County Atty), 4. Jmattingly 1.17.25

SUBJECT

title

Approve Construction Contract No. 2021-052, Change Order No. 4 with Vogel Brothers Building Co. for the Upgrade Lift Station No. 253 (Providence) Project. ($12,216.47 increase; $2,217 CIP amendment and transfer from reserves; revised contract sum to date of $892,638.61, and time extension of 155 days).

body

 

DESCRIPTION

Construction contract 2021-052 with Vogel Brothers Building Company for the Upgrade Lift Station No 253 project was approved by the Board on July 6, 2021.  The summary of the contract total and subsequent change orders is as follows:

 

Item

Board Approval

Additional Time

Amount

New Contract Total

Contract Approval

July 6, 2021

NA

$1,250,092.20

$1,250,092.20

Deductive CO #1

April 12, 2022

NA

($108.003.58)

$1,142,088.62

Deductive CO #2 plus time extension

May 25, 2022

249 days

($261,666.48)

$880,422.14

CO #3 - time extension only

April 13, 2023

162 days

NA

$880,422.14

CO #4 plus time extension

Current

155 days

$12,216.47

$892,638.61

 

After conception of this project, Polk County Utilities adopted a policy that in addition to a standby generator, regional lift stations will include permanent by-pass pumps.  This will aid in reduction of sanitary sewer overflows in the event of a power outage as well as accommodating maintenance and repairs to the lift station.  The County requested a change order to add the permanent by-pass pumps.  This change, as well as some additional temporary by-pass pumping required during construction, totaled $176,744.67.  The summary of the change order is provided on Attachment A. 

 

The contract amount of $1,250,092.20 included contingencies and allowance totaling $164,528.20 consisting of the following:

 

Electrical Contingency                                                                                    $  35,000.00

Instrumentation and Control Contingency                     $  35,000.00

Civil/Site Contingency                                                                                    $  35,000.00

Allowance Work                                                                                                         $  59,528.20

 

This agenda item is requesting an additional $12,216.47 is to cover Change Order No. 4.  In addition, a time extension of 155 days is requested to complete the additional work. The Board approval of Change Order Number 4 will supersede and satisfy the need for other customary contingency release and allowance authorization.

 

The new contract total will be $892,638.61. The project budget is short $2,217 and requires a CIP amendment. 

 

RECOMMENDATION

Approve Construction Contract No. 2021-052, Change Order No. 4 with Vogel Brothers Building Co. for the Upgrade Lift Station No. 253 (Providence) Project and CIP amendment and transfer from reserves. ($12,216.47 increase; $2,217 CIP amendment and transfer from reserves; revised contract sum to date of $892,638.61, and time extension of 155 days).

 

FISCAL IMPACT

Upon the approval of a CIP amendment and transfer from reserves in the amount of $2,217, funding is available in the Utilities Capital Expansion Fund to complete this project.

 

CONTACT INFORMATION

James Tully

Capital Project Manager

(863) 298-4238

 

jamestully@polk-county.net <mailto:jamestully@polk-county.net>