Title: Request Board approve construction contract with Jr. Davis Construction Company., Inc. for the Thompson Nursery Road Extension Phase 1 - Segment 1 project. ($33,523,440.79 one-time expense)
Attachments: 1. Bid 25-420, Construction Contract Package - signed by legal & contractor
Date Action ByActionResultAction DetailsAgenda DetailsVideo
No records to display.
SUBJECT
title
Request Board approve construction contract with Jr. Davis Construction Company., Inc. for the Thompson Nursery Road Extension Phase 1 - Segment 1 project. ($33,523,440.79 one-time expense)
body

DESCRIPTION
The Roads and Drainage Division requested that Procurement solicit bids from qualified contractors for the construction of the Thompson Nursery Road Extension in Winter Haven. The project limits begin at SR 540 and US 17 and extend approximately 1.9 miles to the southeast, ending south of Rifle Range Road (CR 655) and Eloise Loop Road. The scope of work includes, but is not limited to, roadway construction, drainage improvements, pedestrian features, signing and pavement markings, traffic signal installation, and maintenance of traffic.
This project is intended to enhance multimodal mobility along the new roadway with accommodation for pedestrians and bicyclists and will provide bridges over the Wahneta Farms Drainage Canal. Intersections have been designed to improve safety and enhance traffic operations. The new roadway will include curb and gutter and a stormwater collection system to improve drainage conditions.
Bid 25-420, Thompson Nursery Road Extension Phase 1 - Segment 1 project was issued, and seven contractors submitted a bid.
Company
Location
Total
Jr. Davis Construction Company., Inc.
Kissimmee, FL
$ 33,273,440.79
Prince Contracting, LLC
Tampa, FL
$ 33,634,540.00
Cone & Graham, Inc
Tampa, FL
$ 35,532,500.00
Watson Civil Construction, Inc.
St. Augustine, FL
$ 36,484,516.85
Crisdel Group, Inc.
Tampa, FL
$ 38,693,021.37
Hubbard Construction Company
Winter Park, FL
$ 38,915,498.84
RCS Construction Company, Inc
Clermont, FL
$ 42,288,028.88
A recommendation of award was issued to Jr. Davis Construction Company., Inc. and no protests were received. In accordance with Resolution No. 13-066, $250,000.00 was added to the contract for allowance work for a total contract amount of $ 33,523,440.79. The contract time for this project is 1,033 d...

Click here for full text