Legislation Details

File #: 26-2367   
Type: County Manager Status: Agenda Ready
File created: 11/18/2026 In control: Board of County Commissioners
On agenda: 12/1/2026 Final action:
Title: Approve agreement with Kimley-Horn and Associates, Inc. Professional Engineering Services for the Old Dixie Trail – Phase One, a multimodal trail from the trailhead of the Auburndale TECO Trail to the Haines City Trail. (Not-to-exceed $1,986,100.50)
Attachments: 1. RFP 26-066; Professional Services Agreement with Exhibits - FDOT Approved 11.16.26
Date Action ByActionResultAction DetailsAgenda DetailsVideo
No records to display.
SUBJECT
title
Approve agreement with Kimley-Horn and Associates, Inc. Professional Engineering Services for the Old Dixie Trail – Phase One, a multimodal trail from the trailhead of the Auburndale TECO Trail to the Haines City Trail. (Not-to-exceed $1,986,100.50)
body

DESCRIPTION
The Old Dixie Trail project from Auburndale to Haines City will provide a varying 10 foot to 12 foot trail for approximately 13 miles in length.The project begins in Auburndale and traverses along Lake Alfred Road and US 17/92 and terminates in Haines City. The project connects the cities of Auburndale, Lake Alfred, and Haines City. The purpose of this project is to address an existing gap in the regional trail network between Auburndale and Haines City. Other goals of the project are to 1) provide a safe, viable, nonmotorized travel option for commuters and recreational trail users to access area destinations and 2) support quality of life and economic objectives of the surrounding area.
Request for Proposal (RFP) 26-066, Old Dixie Trail from Auburndale to Haines City was issued, and nine vendors submitted proposals. On May 19, 2026, the Board approved the committee’s recommendation to enter into contract negotiations with Kimley-Horn and Associates, Inc. The attached agreement is the result of those negotiations.
Phase One of the Old Dixie Trail project will include Segments 3, 4, and 5, which are currently undergoing the Project Development and Environment (PD&E) study. These segments were selected for design within available funding to provide a connection between Auburndale and the existing trails through Lake Alfred. Phase One will not include Segments 1 and 2 due to the substantial right-of-way acquisition required for those portions of the project.
It is anticipated that Phase One of the project will be completed within 24 months; however, the agreement will remain in effect until all services are complete.

RECOMMENDATION
Request Board approve the agreement with Kimley-Horn a...