File #: 25-0637   
Type: TPO Agenda Item Status: Agenda Ready
File created: 4/4/2025 In control: Transportation Planning Organization (TPO)
On agenda: 4/10/2025 Final action:
Title: Approve Modification to Provide a Time Extension for Consultant Services Authorization (CSA) TPO-20-1009-02-03 with Kimley-Horn and Associates, Inc.to Prepare the Preliminary 2050 Long Range Transportation Plan Update (Part One)
Attachments: 1. AI7_A1_Kimley-Horn CSA 20-1009-02-03 2050 LRTP Scope A_MODIFICATION--edits, 2. AI7_A2_Kimley-Horn 2050 LRTP Scope A
Date Action ByActionResultAction DetailsAgenda DetailsVideo
No records to display.

AGENDA ITEM

title

Approve Modification to Provide a Time Extension for Consultant Services Authorization (CSA) TPO-20-1009-02-03 with Kimley-Horn and Associates, Inc.to Prepare the Preliminary 2050 Long Range Transportation Plan Update (Part One)

body

 

PRESENTER

NA

 

SUMMARY

There is a need for a time extension on the referenced contract.  Staff is proposing to extend the time period to June 30, 2025, to complete the work for this project.  This modification extends the contract by eight (8) months, but does not change the project scope or budget.

 

RECOMMENDED ACTION

Approval of CSA TPO-20-1009-02-03 Modification #1.

 