Approve Change Order No. One (1) to Contract No. 2024-076 with Strickland Construction, Inc. for the Construction of the New Sally Port and Demolition of the Lawrence Crow Building. ($44,597.35 One-time Expense)
body
DESCRIPTION
On November 5, 2024, the Board approved Contract No. 2024-076 with Strickland Construction, Inc. for the Construction of the New Sally Port and Demolition of the Lawrence Crow Building.
During demolition, the contractor encountered existing oversized building foundations that were not identified in the contract's original scope of work or the provided as-built drawings. The foundations were larger than anticipated and require additional work to remove.
Strickland Construction, Inc. has requested approval of Change Order No. One (1) to Contract No. 2024-076 in the amount of $44,597.35 for this out-of-scope work.
RECOMMENDATION
Board approve Change Order No. One (1) to Contract No. 2024-076, in the amount of $44,597.35, with Strickland Construction, Inc. for the Construction of the New Sally Port and Demolition of the Lawrence Crow Building.
FISCAL IMPACT
Funds are available in the General Capital Improvement Fund.