Skip to main content

File #: 25-1863   
Type: Consent Agenda Status: Agenda Ready
File created: 10/6/2025 In control: Board of County Commissioners
On agenda: 10/21/2025 Final action:
Title: Approve Change Order No. One (1) to Contract No. 2024-076 with Strickland Construction, Inc. for the Construction of the New Sally Port and Demolition of the Lawrence Crow Building. ($44,597.35 One-time Expense)
Attachments: 1. CO#1 2024-076 - Constr New Sally Port & Demo LWC
Date Action ByActionResultAction DetailsAgenda DetailsVideo
No records to display.

SUBJECT

title

Approve Change Order No. One (1) to Contract No. 2024-076 with Strickland Construction, Inc. for the Construction of the New Sally Port and Demolition of the Lawrence Crow Building. ($44,597.35 One-time Expense)

body

 

DESCRIPTION

On November 5, 2024, the Board approved Contract No. 2024-076 with Strickland Construction, Inc. for the Construction of the New Sally Port and Demolition of the Lawrence Crow Building.

During demolition, the contractor encountered existing oversized building foundations that were not identified in the contract's original scope of work or the provided as-built drawings. The foundations were larger than anticipated and require additional work to remove.

Strickland Construction, Inc. has requested approval of Change Order No. One (1) to Contract No. 2024-076 in the amount of $44,597.35 for this out-of-scope work.

 

RECOMMENDATION

Board approve Change Order No. One (1) to Contract No. 2024-076, in the amount of $44,597.35, with Strickland Construction, Inc. for the Construction of the New Sally Port and Demolition of the Lawrence Crow Building.

 

FISCAL IMPACT

Funds are available in the General Capital Improvement Fund.

 

CONTACT INFORMATION

Keith R. Tate, Director

Facilities Management Division

863-534-5511

keithtate@polk-county.net