In accordance with the Resolution passed by the Board on January 7th regarding Road Closure Requests, the staff is bringing the following list of road closures received since January 7th for the Board to approve:
1. Newman Circle East - 12 Days for Culvert Replacement
2. Homosassa Drive - 45 Days for Water Main and Sewer Extension under the Road
3. Redfin Drive - 12 Days for Sewer Main Extension under the Road
RECOMMENDATION
Approve Road Closure Requests greater than 5 Days.
FISCAL IMPACT
No Fiscal Impact