SUBJECT
title
Request Board approve 1) Construction contract with Strickland Construction, Inc. for the new Lakeland Hills EMS Station ($3,695,394.00 one-time expense) and 2) CIP amendment and budget transfer from EMS Impact Fee Reserve for Future Capital in the amount of $147,731.00 to fully fund the project.
body
DESCRIPTION
The Facilities Management Division requested Procurement to solicit bids from qualified contractors who were interested in the construction of a 7,381 square-foot EMS Station, which includes three pull-thru apparatus bays and living quarters to accommodate six medical personnel. The facility is located at 650 Robson Street E., Lakeland, FL.
Bid 26-041, Lakeland Hills EMS Station was issued, and eleven contractors submitted a bid. The lowest responsive bid was submitted by Strickland Construction, Inc.
Company Location Total________
Strickland Construction, Inc. Lakeland, FL $3,519,423.00
Blackwater Construction Services Gainesville, FL $3,807,424.00
Everett Whitehead & Son, Inc. Winter Haven, FL $3,886,344.00
d/b/a Whitehead Construction
Henkelman Construction, Inc. Lakeland, FL $3,895,530.00
NuJak Companies, Inc. Lakeland, FL $3,977,525.00
Mulligan Constructors, Inc. Orlando, FL $4,004,535.00
Peachee Construction, Inc. Lakeland, FL $4,144,000.00
Register Construction & Lakeland, FL $4,334,335.00
Engineering, Inc.
SEMCO Construction, Inc. Bartow, FL $4,440,000.00
L. Cobb Construction, Inc. Wauchula, FL $4,471,928.04
J.E. Decker Construction Group, LLC Lakeland, FL $4,597,199.00
d/b/a Decker Construction
A recommendation of award was issued to Strickland Construction, Inc., and no protests were received. In accordance with Resolution No. 13-066, $175,971.00 was added to the contract for allowance work for a total contract amount of $3,695,394.00. The contract time for this project is 365 days. Allowance time for the project is 54 days.
The total CIP budget for this project is $4,077,450.00. T...