Title: Approve Construction Contract with Timmons Contracting Inc. for the Rock Ridge Rd Bridge Replacement project ($2,229,446.00 one-time expense)
Attachments: 1. Bid 26-003 Contract Signed by Vendor, 2. Bid 26-003 Contract Noah and Vendor Signed, 3. Arch Insurance Company - Company Profile - Best's Credit Rating Center, 4. Surety Bonds - List of Certified Companies, 5. The Continental Insurance Company - Company Profile - Best's Credit Rating Center, 6. Westchester Surplus Lines Insurance Company - Company Profile - Best's Credit Rating Center
Date Action ByActionResultAction DetailsAgenda DetailsVideo
No records to display.

SUBJECT

title

Approve Construction Contract with Timmons Contracting Inc. for the Rock Ridge Rd Bridge Replacement project ($2,229,446.00 one-time expense)

body

 

DESCRIPTION

The Roads and Drainage Division requested Procurement to solicit bids from qualified contractors who were interested in the construction of a new 40 foot geosynthetic reinforced soil integrated bridge system on Rock Ridge Rd in Lakeland. The project primarily consists of bridge construction, roadway construction, erosion control, clearing and grubbing, excavating, stabilization, constructing retaining walls, and maintenance of traffic.

Bid 26-003, Rock Ridge Rd Bridge Replacement was issued, and seven contractors submitted a bid.

Company

Location

Total

Timmons Contracting Inc.

Bradenton, FL

$2,123,282.00

Gosalia Concrete Constructors, Inc.

Tamp, FL

$2,154,663.00

Cone & Graham, Inc.

Tampa, FL

$2,166,562.84

Central Concrete Products, Inc.

Bartow, FL

$2,346,210.04

Southland Construction, Inc.

Apopka, FL

$2,350,000.01

Hubbard Construction Company

Winter Park, FL

$2,548,967.56

Cathcart Construction Company Florida, LLC

Winter Springs, FL

$2,850,027.00

 

A recommendation of award was issued to Timmons Contracting Inc., and no protests were received. In accordance with Resolution No. 13-066, $106,164.00 was added to the contract for allowance work for a total contract amount of $2,229,446.00. The contract time for this project is 180 days to final completion. Allowance time for the project is 27 days.

 

RECOMMENDATION

Request Board approve a construction contract with Timmons Contracting Inc. in the amount of $2,229,446.00 for Bid 26-003, Rock Ridge Rd Bridge Replacement.

 

FISCAL IMPACT

Funding is available in the Transportation Trust Fund.

 

CONTACT INFORMATION

Ken Brush

Procurement Contracts Manager

863.534.6727