SUBJECT
title
Approve the First Modification to the Contract Operator Preliminary Works Service Agreement (Action)
body
DESCRIPTION
On September 20, 2023, the Southeast Wellfield Project Board of Directors and the West Polk Project Board of Directors entered into an agreement with US Water Service Corporation / ACCIONA Agua Corporation Joint Venture to provide contract operator preliminary works services for the two projects.
For the preliminary phase of work, the contract operator will provide preconstruction and design review services ($104,291.78), as well as construction review services ($304,204.42), for a total cost of $408,496.20. The final phase of work is the actual operation of the facilities. That final operation contract will be negotiated once the design level reaches 90% complete.
As the PRWC continues to acquire land for production well sites and begins early construction on the transmission main, property and asset maintenance/oversight activities need to begin. These activities include:
1) Installation and maintenance of property (landscape installation, grass/shrub cutting, etc.);
2) Installation and maintenance of fencing and securing of wells;
3) Periodic pipeline assessment visits (Insuring pressurization, chlorine residuals, etc.)
4) Location request services for the pipeline (Florida Sunshine 811 service);
5) Emergency response services.
During the negotiations for the subject contract, the Cooperative knew that there would be a need for limited services before the operations agreement was negotiated and a brief paragraph was inserted into the Agreement for that purpose. This First Modification further describes the needed services and sets a procedure for the Cooperative to request such services.
PRWC staff have negotiated a modification to the Preliminary Works Service Agreement for the contract operator to perform these services on a as-needed, work order basis. As services are needed, the PRWC and Contract Operator will nego...
Click here for full text