File #: 25-0939   
Type: Consent Agenda Status: Agenda Ready
File created: 5/23/2025 In control: Board of County Commissioners
On agenda: 6/17/2025 Final action:
Title: Approve Change Order No. 1 to Contract No. 2024-081 with Kaminga & Roodvoets, Inc (Contractor) for the Indian Woods Trails Drainage Improvement Project ($154,792.62 one-time expense).
Attachments: 1. 2. Change Order No. 1, 2. 3. LAR - Change Order No. 1 (Contract 24-081), 3. 4. KR Driveway Quote - Backup
Date Action ByActionResultAction DetailsAgenda DetailsVideo
No records to display.

SUBJECT

title

Approve Change Order No. 1 to Contract No. 2024-081 with Kaminga & Roodvoets, Inc (Contractor) for the Indian Woods Trails Drainage Improvement Project ($154,792.62 one-time expense). 

body

DESCRIPTION

On November 5, 2024, the Board approved Contract No. 2024-081 with the Contractor in the amount of $1,304,405.30 to construct Indian Woods Trail Drainage Improvement Project (Project).  The goal of the Project is to resolve localized flooding and standing water conditions that persist within the open ditch drainage system along Indian Woods Trail, Tomaka Run, and Tocoi Path.  Construction of the Project is ongoing and is being funded by the American Rescue Plan Act.  

The Project primarily consists of re-grading the open ditch system, piping the north outfall to Cambell Road from Indian Woods Trail, desilting all the existing culverts, and replacing seven driveway pipes that were deemed to be adversely impacting the drainage system. 

After the Contractor completed the desilting and inspection of all the existing culverts, it was determined an additional eleven driveway culverts are in failing condition.  This Change Order will add the replacement of these pipes and driveway aprons to Contract 2024-081 for a lump sum price of $154,792.62.  Change Order No. 1 will also add 20 additional days of contract time.  

RECOMMENDATION

Request the Board approve Change Order No. 1 to Contact No. 2024 with the Contractor in the amount of $154,792.62 resulting in a new total contract amount of $1,459,197.92.

FISCAL IMPACT

Funds in the amount of $154,792.62 are available in the Transportation Millage Fund within the Roads and Drainage 5 Year CIP.

CONTACT INFORMATION

Conner Updike, P.E.

Drainage Engineer

Roads & Drainage Division

(863) 535-2276

 

Jay M. Jarvis, P.E.

Roads & Drainage Division Director

(863) 535-2200