File #: 24-0998   
Type: PRWC Agenda Item Status: Agenda Ready
File created: 6/12/2024 In control: Polk Regional Water Cooperative
On agenda: 7/24/2024 Final action:
Title: Approve Change Order to the Youngquist Brothers Drilling, Inc. Contract for the Construction of West Polk Wellfield Injection Well #1 (Action)
Attachments: 1. Youngquist Change Order costs exhibit, 2. H.2 Youngquist Change Order for Signatures
Date Action ByActionResultAction DetailsAgenda DetailsVideo
No records to display.
SUBJECT
title
Approve Change Order to the Youngquist Brothers Drilling, Inc. Contract for the Construction of West Polk Wellfield Injection Well #1 (Action)
body

DESCRIPTION
On March 22, 2023 the Southeast Board of Directors approved a contract with Youngquist Brothers Drilling, Inc. for the construction of the Southeast Injection Well 1 (SEIW-1). Construction of SEIW-1 is now concluding with final testing occurring in August and September of 2024. The well was constructed to a cased depth of 3,300' with a total depth of 8,050'. Preliminary testing has indicated that the well will be able to accept the full amount of concentrate water from Phase 1 of the project. The total cost for the SEIW-1 is $18,888,000.

At the July 24, 2024 PRWC Southeast Wellfield Board of Directors meeting the Board will be asked to approve a contract amendment to allow construction of the West Polk Injection Well 1 (WPIW-1). In addition to the contract amendment, and in order to proceed with the construction of WPIW-1, the West Polk Board of Directors will be asked to consider a change order to the contract which allocates funding to the construction of WPIW-1.

The WPIW-1 Change Order (attached) provides for the following:
1) A construction contract time of an additional 1000 calendar days from Notice to Proceed to Final Completion with a substantial completion date of June 24, 2027;
2) An additional Construction Contract Price of $23,349,310 for WPIW-1 and the Dual Zone Monitor Well.

The full contract price is now $42,237,310 for both the Southeast and West Polk Projects injection wells and necessary monitor wells.

RECOMMENDATION
Approve the Change Order to the Youngquist Brothers Drilling, Inc. contract for the construction of West Polk Injection Well 1.

FISCAL IMPACT
The WPIW-1 is anticipated to cost $18,762,600 (inclusive of stand-by time and contingency, well acidification, and final demobilization costs) and the dual zone monitor well is anticipated to cost $4,586,710...