SUBJECT
title
Approval of Final Closeout for North Central Landfill Constructed Wetlands Treatment System Contract 2023-022. Change Order decrease of $347,410.52 is needed to close out the contract.
body
DESCRIPTION
For this final closeout, a contract amount decrease is being requested, in the amount of $347,410.52, as a final reconciliation Change Order No. 3. This amount is the remaining contingency and allowance balance that is on Contract No. 2023-022. Please see the attached documents which are required for proper final closeout: Final Change Order for cost decrease; Signed Final & Substantial Completion Forms; Consent of Surety; Final Pay Application No. 18.
Details:
Final Pay Application No. 18 to Vendor (one-time expense): $566,449.99
Change Order No. 3 (decrease): $347,410.52
Contract Contingency (not used): $100,000.00
Contract Allowance: $250,000.00
Contract Allowance Used: $2,589.48 (see Pay App. No. 18)
$347,410.52 = ($100,000.00+$250,000.00)-$2,589.48)
RECOMMENDATION
Request Board approval for Change Order No. 3, and final closeout for Contract No. 2023-022 (NCLF Constructed Wetlands Treatment System).
FISCAL IMPACT
Funds are available in the Solid Waste Funds.
CONTACT INFORMATION
Beau McCall
Polk County Solid Waste