File #: 22-667   
Type: PRWC Agenda Item Status: Closed
File created: 9/6/2022 In control: Polk Regional Water Cooperative
On agenda: 9/21/2022 Final action:
Title: Authorize Executive Director to execute Change Order No. 5 with Carollo Engineers, Inc. to provide construction phase services for Test Production Well #3 (Action Item).
Attachments: 1. 22 08 31 SEWF-TPW#3 Const Svs-CO5_Executed_By_Carollo G.7
Date Action ByActionResultAction DetailsAgenda DetailsVideo
No records to display.

SUBJECT

title

Authorize Executive Director to execute Change Order No. 5 with Carollo Engineers, Inc. to provide construction phase services for Test Production Well #3 (Action Item). 

body

 

DESCRIPTION

In September of 2021, the Board authorized the Executive Director to execute a change order with Carollo Engineers (a.k.a. TeamOne) for up to $113,000 to provide design, environmental permitting, and survey services for the Southeast Wellfield Test Production Well (TPW) #3.  Change Order No. 3 was subsequently issued on October 7, 2021.  Design of the well is complete, and a drilling contractor has been selected for the construction of TPW #3.  The professional hydrogeologist services outlined in Change Order No. 5 are required to support TPW #3 construction and consist of daily on-site observation of drilling activities, well testing support (including a 14-day aquifer performance test), and the preparation of a Well Completion Report.  TPW #3 will be converted to a production well for Phase 1 of the Southeast Wellfield Project.  This project is co-funded by the SWFWMD under Grant Agreement No. 21CF0003731.

 

RECOMMENDATION

Authorize Executive Director to execute Change Order No. 5 with Carollo Engineers, Inc. to provide construction phase services for Test Production Well #3.      

 

FISCAL IMPACT

Fiscal impact in the amount of $351,864, with 50% reimbursement by SWFWMD in the amount of $175,932. 

 

CONTACT INFORMATION

Mark Addison